Project Management Pert Essay

1633 words - 7 pages

Chapter 13 Project Management

Characteristics of a “project”:
■  A

project is unique (not routine), ■  A project is composed of interrelated sub-projects/activities, ■  It is associated woth a large investment.

What is Project Management
■  To

schedule and control the progress and cost of a project.

PERT/CPM:
■ 

Input:
–  –  – 

Activities in a project; Precedence relationships among tasks; Expected performance times of tasks. The earliest finish time of the project; The critical path of the project; The required starting time and finish time of each task; Probabilities of finishing project on a certain date; ...view middle of the document...

■ 

Output:
–  –  –  –  – 

PERT/CPM is ...view middle of the document...

■  The larger the variance, the more spreadout the random values. ■  The square root of variance is called standard deviation.

Example, Foundry Inc., p.525
Activity a m b t variance

A B C D E F G H

1 2 1 2 1 1 3 1

2 3 2 4 4 2 4 2

3 4 3 6 7 9 11 3

Critical Path
•  •  • 

It is the “longest” path in the PERT network from the start to the end. It determines the duration of the project. It is the bottle-neck of the project.

Time and Timings of an Activity:
•  •  •  •  •  • 

t=estimated performance time; ES=Earliest starting time; LS=Latest starting time; EF=Earliest finish time; LF=Latest finish time; s=Slack time of a task.

Uses of Time and Timings
■  Earliest

times (ES and EF) and latest times (LS and LF) show the timings of an activity’s “in/out” of project. ■  ES and LS of an activity tell the time when the preparations for that activity must be done. ■  For calculating the critical path.

Computing Earliest Times
Step 1. Mark “start” node: ES=EF=0. Step 2. Repeatedly do this until finishing all nodes:
For a node whose immediate predecessors are all marked, mark it as below:
•  • 

ES = Latest EF of its immediate predecessors, EF = ES + t
• 

Note: EF=ES at the Finish node.

Computing Latest Times:
Step 1. Mark “Finish” node:
LF = LS = EF of “Finish” node.

Step 2. Repeatedly do this until finishing all nodes:
For a node whose immediate children’s are all marked with LF and LS, mark it as below:
•  • 

LF = Earliest LS of its immediate children, LS = LF – t
• 

Note: LS=LF at Start node.

Computing Slack Times
• 

For each activity:
–  slack

= LS – ES = LF – EF

Foundry Inc. Example
• 

Calculate ES, EF, LS, LF, and slack for each activity of the Foundry Inc. example on its PERT network, given the data about the project as in the next slide.

Example, Foundry Inc.
Activity a m b t variance

A B C D E F G H

1 2 1 2 1 1 3 1

2 3 2 4 4 2 4 2

3 4 3 6 7 9 11 3

2 3 2 4 4 3 5 2

0.111 0.111 0.111 0.444 1 1.777 1.777 0.111

A
ES= LS=

2
EF= LF=

C
ES= LS=

2
EF= LF=

F
ES= LS=

3
EF= LF=

slack=

slack=

slack=

Start
ES=EF= LS=LF=

E
ES= LS=

4
EF= LF=

H
ES= LS=

2
EF= LF=

Finish
ES=EF= LS=LF=

slack= B
ES= LS=

slack= G
ES= LS=

3
EF= LF=

D
ES= LS=

4
EF= LF=

5
EF= LF=

slack=

slack=

slack=

Network for Foundry Inc.

Example of Hospital Project:
■  Calculate

ES, EF, LF, LS and slack of each activity in this project on its PERT network, given the data about the project as in the next slide.

Example: A Hospital Project
Activity
A B C D E F G H I J K

Immediate Predecessor(s)
— — A B B A C D A E, G, H F, I, G

Performance time t (weeks)
12 9 10 10 24 10 35 40 15 4 6

F
ES=

10
EF= LF=

A
ES= LS=

12
EF= LF=

LS=

K
ES= LS=

6
EF= LF=

slack= I
ES= LS=

15
EF= LF=

slack=

slack=

slack= Start
ES=EF= LS=LF=

G 10
EF= LF= ES= LS=...

Other Essays Like Project Management Pert

Random Essay

3094 words - 13 pages ' manufacturing methodologies and the Program Evaluation and Review Technique framework (PERT). The report outlines the main features of these methodologies and the advantages and limitations of them with specific reference to their usefulness in a variety of practical situations. The report concludes that each of the methodologies has something to offer and that any management decision must be based on the goals and objectives of the company and its

Describe Some Of The Things That Can Be Done In The Early Stages To Ensure That A Project Is Set Up With A Reasonable Degree Of Success

2941 words - 12 pages , p. 562) mentioned "when scheduling a project, the project manager must know the duration of each task, the order in which the activities will be performed, the start and end times for each task, and who will be assigned to each specific." Some project managers use tools and techniques to support their management of a project. These tools include the Project Evaluation Review Technology (PERT) chart and the Gantt chart. The PERT chart is a

Systems Analysis and Design

1908 words - 8 pages the group’s PERT diagram as a guide that shows a projected target completion in the month of July for this project. A PERT diagram’s time does not account for unforeseen changes such as a forced employment reduction and can be updated as the project progresses (Picariello, 2010) Ouvera and Stan feel that eliminating the testing portion at this point would be an acceptable loss versus my suggestion of delaying it and pushing out the

Pert Chart Analyzes

1130 words - 5 pages Low Capston AIU ➢ Analyzes the organization’s basic legal, social, and economic environments. ➢ Analyzes the organization’s managerial, operational, and financial issues including: ➢ Project Management ➢ Project Timelines ➢ Critical Paths and Contingencies ➢ Staff Needs and Tools ➢ One Gantt Chart Example (project related) ➢ One Pert Chart Example (project related) ➢ Analyzes the impact of

Program Management

1482 words - 6 pages 1. Prepare opening comments that give the class an overview of project management. To understand what project management is we must first define what a project is. A project is a structured coordinated series of event, which result in a final deliverable. The deliverable in questions can be service oriented or produce a product to be delivered. A defined project will typically have a predetermined start and end date for the tasks within the

It/205 Week 8 Checkpoint

630 words - 3 pages would have taken to control the risk would be the implementation of the device, meaning all activities working together toward one main goal, the adoption of the device and technology. Another step I would take is to make available Project Management Software which automate the creation of Gantt and PERT charts, ability to define and order tasks, assign resources to tasks establish start and end dates for the tasks, tracking progress, and

PM 586 Final Exam (Latest) - Assignment

1118 words - 5 pages himself / herself 12. A project manager desires a work breakdown structure that goes through 6 levels of detail. Level 3 through level 6 would most likely be prepared by: • Customer • Subject matter experts • Project manager • Project sponsor 13. In which project life cycle phase does quality begin? • Initiation / planning • Monitoring & control • Closure • Implementation 14. Project management restructuring

The History of Operations Management

4735 words - 19 pages values and standard deviations for each activity. A PERT CHART [pic] CRITICAL PATH METHOD ( duPont) The Critical Path Method is an important part of PERT. According to Heizer and Render (2008) the “Critical Path Method (CPM) is a project management technique that uses only one time factor per activity”. It was developed in 1957 by Morgan R. Walker of DuPont and James E. Kelly Jr. of Remington Rand and like PERT is used to

Project Plan

4210 words - 17 pages CAREER EXPLORATION PROGRAM (PROJECT FIGARO) PROJECT PLAN APRIL 2015 Document versions and key changes: Version | Issue Date | Key Changes | Author | 2.0 | April 25, 2015 | Updated WBSUpdated PERT/CPMUpdated Organizational Chard | Monitoring & Control Committee | Approved by: Version | Name | Function | Signature/Email | 2.0 | Sorono, Terence | Project Sponsor | | TABLE OF CONTENTS Executive Summary of Project 1

Game Essay Final

4527 words - 19 pages , as Jason observes: "I have adopted industry standard terminology that can be understood by any reader with a rudimentary knowledge of project management. I have not adopted the complicated acronym-based terminology that is prevalent throughout industry. As such, you will not read about undertaking a PERT (project evaluation review technique) or CPA (critical path analysis), but you will read about how to create practical plans for managing time

Project Management

3401 words - 14 pages Examination Paper of Project Management Certification IIBM Institute of Business Management Examination Paper MM.100 Project Management Certification Guidelines for paper  Total No. of Questions is 100.  The minimum passing marks is 50%.  Each Question carries 1 mark.  Answer all the Questions. Multiple Choices: 1. A_______ is a temporary endeavor undertaken to create a unique product, service or result. a) Program b) Process c) Project d

Related Papers

Project Management Essay

2260 words - 10 pages and translating into PEP (Program Evaluation Procedure) (Awan, 2010). PERT, performing as a management method, was designed to handle a plethora of contractors for devising, creating and experimenting the POLARIS submarine and missile systems. Both CPM and PERT have been used currently as important network analysis and project management tools of industrial and military constructions to plan, schedule and control sophisticated projects. These

History Of Project Managment Essay

622 words - 3 pages HISTORY OF PROJECT MANAGMENT 01-Jun-13 UMMARA MUSHTAQ 2123224 HISTORY OF PROJECT MANAGEMENT PROJECT MANAGEMENT: Project management is the discipline of planning, organizing, motivating, and controlling resources to achieve specific goals. Starting in the early 1960s, businesses and other organizations began to see the benefit of organizing work around projects. This project-centric view of the organization evolved

It511 Unit3 Essay

2429 words - 10 pages Information Systems Project Management Unit 3 Assignment 1 Kaplan University IT511 Professor Chad McAllister February 16, 2013 1. Explain project scope management in terms of its processes. Scope management is the process of defining and controlling the work that is or is not included in the project (Schwalbe, 2012). This outlines to the team and stakeholders the product that will be produced and the processes that will be used

Word Choice Essay

877 words - 4 pages Birla Institute of Technology & Science, Pilani Work-Integrated Learning Programmes Division Second Semester 2013-2014 Course Handout Course No. : MM ZG523/CM ZG523/HHSM ZG519/QMJ ZG523 Course Title : PROJECT MANAGEMENT Instructor : Arun Maity Course Description: Concepts and techniques of project formulation, evaluation and implementation; Project planning and scheduling; Risk management; Time-cost trade off